Founder’s previous experience
Road and Highway Structures Projects in Kocaeli — Ro-Ro Junction–Seka Tunnel Section
- Location
- Kocaeli
- Period
- 2025
- Sector
- Highways and interchanges
- Role
- Geotechnical and Geological Department Manager / Geotechnical Design
This project is a work our founder Yusuf Nazlıoğlu was involved in during a previous role, outside Vertex Proje.
Scope of services
Bearing capacity, slope stability, deep foundation and ground improvement design for bridges and connecting roads.
About the project
As part of the detailed design works, geotechnical calculations and numerical analyses were performed and reviewed for Side Road-6, Side Road-7, the Roundabout-1 Bridge and the Roundabout-2 Bridge.
The work included geotechnical assessments, bearing capacity and slope stability analyses, deep foundation design and the selection and design of suitable ground improvement methods.